How to read this finding
All three values describe the announced plan. They are not measurements of investment already spent, chips installed, or operating capacity. Chip count is the report’s approximate translation of the proposed capacity.
An announced US AI infrastructure project targeting $500B of investment and 10GW of capacity over four years, backed by SoftBank, MGX, Oracle, and OpenAI. These were plans, not completed capacity.

All three values describe the announced plan. They are not measurements of investment already spent, chips installed, or operating capacity. Chip count is the report’s approximate translation of the proposed capacity.
Evidence you can use
January 2025 announcement as recorded in the report
| Measure | Reported value | Definition and source |
|---|---|---|
| Planned investment | $500B | Over four years2025 report, slide 121 (PDF page 122) |
| Planned capacity | 10GW | Proposed US buildout2025 report, slide 121 (PDF page 122) |
| Implied chip count | More than 4 million | Report estimate2025 report, slide 121 (PDF page 122) |
All three values describe the announced plan. They are not measurements of investment already spent, chips installed, or operating capacity. Chip count is the report’s approximate translation of the proposed capacity.
Historical snapshot published October 9, 2025. This web edition was prepared on October 10, 2026 from the online deck and original launch posts. Findings and forecasts retain their original time frame.
Benaich, Nathan. “What was Stargate in the 2025 report?.” State of AI Report 2025. Historical report snapshot; web edition prepared 2026-10-10.